Schedule of Values - Bid Items
Phase III Construction - Stage |
Four Hills Landfill
Nashua, New Hampshire
(Revised February 2019)
Estimated
Construction Items Quantity
(w/units)
Temporary Slope Diversion Swale 670 LF LF
Drain Manhole 1 LS LS
Culverts
a. C-1 (36-inch diameter CPP LS LS
b. C-2 (36-inch diameter CPP LS LS
c. C-3 (18-inch diameter CPP LS LS
d. C-4 (24-inch diameter CPP LS LS
Topsoil and AC AC
Gravel Road SY SY
Extend Groundwater Wells LF LF
Litter Control Fence
a. Install Litter Control Fence LF LF
b. Install New Litter Control Fence LF
Guardrail LF
As-Built Dra LS
Payment Bond LS
Performance Bond LS
Bid Price
Bid Unit Prices Extended
($/units) Prices ($)
20190110 Schedule of Values-Rev1.xlsx Page 2 of 3 Sanborn Head & Associates, Inc.