March 11, 2019
b. ENGINEER’s structural division shall evaluate the necessary
concrete modifications to allow installation of new screen in
existing influent channels. Summarize findings in draft TM.
c. ENGINEER’s instrumentation division shall summarize the
existing control system and recommended modifications associated
with new screen installation in draft TM.
d. ENGINEER’ s electrical division will summarize the existing
electrical gear and recommended modifications associated with
new screen installation in draft TM.
e. ENGINEER does not expect there to be a need for Civil or
Mechanical division specific TMs. Minor upgrades associated with
these divisions shall be included in other TMs within the PDR.
ENGINEER will hold two progress meetings to discuss draft TM and site
visits. Input from meetings shall be incorporated into updated TM’s.
ENGINEER shall finalize TM’s based upon input from the City and
include in the Preliminary Design Report.
Prepare draft Preliminary Design Report (PDR) and drawings.
1,
Prepare draft Preliminary Design Report (PDR) that includes all technical
memorandums, final design criteria, preliminary drawings and outline
specifications.
Advise OWNER if additional reports, data or other information or services
are necessary and assist OWNER in obtaining such reports, data or other
information and services.
Prepare preliminary construction cost estimate
1.
Based on the information contained in the Preliminary Design documents,
submit to OWNER a Construction Cost Estimate.
Finalize Preliminary Design Report (PDR)
1.
Submit a draft of the Preliminary Design document to, and meet to review
with OWNER.
Receive OWNER comments and provide written response to all comments
to satisfaction of OWNER. Submit final Preliminary Design documents to
DIVISION for review.
The draft preliminary design report shall be submitted within 45 days of
receiving authorization to proceed. Assume OWNER completes review
and issues authorization to proceed with final design within 14 days of
receiving draft preliminary design report.