CMA ENGINEERS, INC.
PROJECT TASKS i
HOURS COST ($)
DESIGN PHASE
1.0 - ENGINEERING STUDY CMA Engineers 404 | $ 46,366
HSI 339 1 $ 28,183
Terracon 94/$ 15,895
Ironwood 88 | $ 7,135
Total 925 | $ 97,579
2.0 - PRELIMINARY DESIGN CMA Engineers 3911 $ 43,350
Ironwood 51/$ 3,948
Total 442 |$ 47,298
3.0 - FINAL DESIGN CMA Engineers 319 | $ 36,471
Ironwood 53 | $ 3,976
Total 372 | $ 40,447
DESIGN PHASE TOTAL: 1,739 | $ 185,324
P-2947 Nashua Fee 190524 (ENG) 5/24/2019