NEGOTIATED
ESTIMATE
Estimated Project Cost Breakdown
CMA ENGINEERS, INC.
PROJECT TASKS
HOURS COST ($)
DESIGN PHASE
1.0 - ENGINEERING STUDY CMA Engineers 3701 $ 42,017
HSI 303 | $ 25,079
Terracon 901 $ 14,551
Ironwood 76] $ 6,094
Total 839 | $ 87,741
2.0 - PRELIMINARY DESIGN CMA Engineers 348 | $ 37,848
Ironwood 48 | $ 3,688
Total 396 | $ 41,536
3.0 - FINAL DESIGN CMA Engineers 283 | $ 32,311
Ironwood 641 $ 4,810
Total 347 1$ 37,121
DESIGN PHASE TOTAL: 1,582 | $ 166,398
P-2947 Nashua Fee 190701 (NEG) 7/1/2019