Preliminary EOPC
The itemized EOPC from the Engineering Study will be updated and expanded to reflect the
advancement to the Preliminary Design level. The streamlined itemized EOPC will include
updated line items, contingencies, and a construction services cost estimate.
Suémission of Preliminary Plans
Plans and documentation will be submitted to City (electronic format only) and the NHDOT (2
hard copies & electronic format) for review and approval. Efforts associated with this task will
include incoproatation of City comments/input for draft preliminary paln review and
development of the the complete submittal package. Included will be ail the materials,
comments, and outcomes of work developed in the Preliminary Design with plans in 11” X
17” format. A transmittal letter will be included that highlights changes, refinements to the
design and Engineering Study comments resolution. All the documentation and plans will also
be submitted to NHDOT electronically (PDF format).
Project Managemen?
CMA project manager will coordinate regularly by email and by phone with NHDOT/City staff,
subconsultants, and project team members; and will complete monthly project status reports
and invoices (3 months assumed).
Phase 3.0 - Fina! Design Plans
3.02
3.63
Final Design Plans
This phase of the project will involve the further development of Preliminary Plans into Final
Design plans for bidding and construction. These plans (see Section 2.01) will incorporate
comments resulting from the Preliminary Plan review. A comment review meeting with the
City is included.
Siructural Final Design
Based on comments received during the Preliminary Design phase, the structural design will
be developed to include fully detailed plans, calculations, and specifications.
lighting and Landscape Archiieciure
Based on review comments received from the City and NHDOT, refine and advance the
Preliminary Design. Construction drawings and details will be prepared to a level of detail
suitable for competitive public bidding.
a. Final Design Documents (Plans and Specifications)
Upon receiving approval to proceed, prepare detailed plan set and technical
specifications.
b. Submit Final Design
Submit Phase 3.0 Final 100% Design documents to CMA Engineers for distribution to
the City and NHDOT for approval.