No. 1
PROJECT NAME: TRANSIT —2 35’ ELECTRIC HYBRID GILLIG BUSES
OWNER’S CONTRACT NO:
EXECUTED CONTRACT DATE: JANUARY 18, 2019
GWNER: City of Nashua, NH
OWNER’ s Purchase Order NO.:
CONTRACTOR: GILLIG
ENGINEER: NA
You are directed to make the following changes in the Contract Documents:
Description:
In August 2018, the Nashua Transit System (NTS) was awarded a 1.1 million dollar Low-No Emission grant from the
Federal Transportation Administration (FT A) to purchase two electric hybrid diesel buses.
The City entered into a contract with Gillig on January 18. 2019 for the following amounts:
2-35 FT Electric Diesel Hybrid Bus - $679,937 per bus
Total cost of 2 buses = $1,359,874
During February and March of 2019. the City of Nashua and Gillig went through the pre-production review of the bus build
and a number of items were added or changed to enhance the safety and functionality of the new fleet.
The additional items and or changes resulted in a credit of $470 for the two buses, and include the following:
e Addition of 1 Quantum wheelchair restraint
Re-ireadable tires
o
2 Insight Prime Plus Seats
® Gerflor Flooring
e Removal of Tablet Holder
e Replacement of Integrated Camera System to standard Mirrors
e Addition of Rear View Camera
Bus Size Original Cast Additional Cost Revised Cost
Bus | $679,937 $572 $680,509
Bus 2 with Quantum $679,937 ($1042) Credit $678,895
Wheelchair Securement
System
Change Order #1 lof2
Gillig Electric Hybrid buses