95
Doc #: 6
Ref. Document:
PROJECT NAME: Date: 4-Sep-19
Nashua Energy Recovery Upgrade
PROJECT NO: 181012
PHASE
COST SUMMARY SHEET
Mechanical Room Painting
A McC Labor (Recap Sheet): $4,282.10
B Mc Materials, & Equipment (Recap Sheet): $453.00
Cc MCG Fee (A x 15%) + (B x 10%): $687.62
D Subtotal MC Work (A+B+C): | $ 5,422.72
E Total Subcontractors (Below): $10,875.00
F McC Mark-up on Subcontractor Work (5%): | $ 543.75
G Bond (1%) and General Liability (1%): $336.83
Total Proposal (D+E+F+G): $ 17,178.30
SUBCONTRACTOR SUMMARY
Subcontractor Description
Arthur Cole painting Pressure Wash and paint the mechanical room
Amount
10,875.00
10,875.00
$
$
$
$
3
3
3
$
Total Subcontractors: