Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$129,900
Original Contract Times
Ready for final payment:
CHANGE IN CONTRACT TIMES:
Substantial completion: N/A
December 2, 2019
Net changes from previous Change Orders
30
Net change from previous Change Orders
0 days
Contract Price prior to this Change Order
$129,900
Ready for final payment:
Contract Times prior to this Change Order
Substantial completion: N/A
December 2, 2019
Net Increase (deerease} of this Change Order
$42,980
Net Increase ¢decrease} of this Change Order
7 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$172,880 Substantial completion: N/A
Ready for final payment: December 9, 2619
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature}
Date: Date:
(Authorized Signature)
Date:
{Authorized Signature)
Change Order # 1 2 of 2
Monica Dr Drainage Improvements