Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$2,135,950.00
CHANGE IN CONTRACT TIMES:
Original! Contract Times
Ready for final payment:
Substantial completion: October 24, 2022
December 23, 2022
Net changes from previous Change Orders
$0
Net change from previous Change Orders
0 days
Contract Price prior to this Change Order
$2,135,950
Ready for final payment:
Contract Times prior to this Change Order
Substantial completion: October 24, 2022
December 23, 2022
Net Increase (decrease) of this Change Order
$500,000.00
Net Increase ¢(deerease) of this Change Order
0 days
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$2,635,950.00 Substantial completion: October 24, 2022
Ready for final payment: December 23, 2022
RECOMMENDED: ACCEPTED: APPROVED:
By: By: By:
DPW Contractor Mayor Jim Donchess
Engineer Owner
(Authorized Signature) (Authorized Signature) (Authorized Signature)
Date: Date: Date:
2022 Sewer Replacement Project 2 of 2 Change Order #1