Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 8/3/2022 - P51

Finance Committee - Agenda - 8/3/2022 - P51

By dnadmin on Sun, 11/06/2022 - 21:46
Document Date
Thu, 07/28/2022 - 10:40
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 08/03/2022 - 00:00
Page Number
51
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__080320…

CRANE AND HOIST
CRANE BUILDERS, INSTALLERS AND TECHNICIANS

information is required, it may be an additional cost.

¢ Load testing not included unless otherwise stated in the main body of the quote

¢ If Mass Crane and Hoist is installing the runway system it will be leveled and braced per CMAA
specifications.

¢ If the runway structure is existing or being provided by others it is assumed the runway is/will be installed,
leveled, braced, and aligned per CMAA. It will be an additional cost if the runway is not installed per
CMAA specifications.

¢ Customer is responsible for the ability of the building to support the load imposed upon it by the
installation of the hoisting equipment. Mass Crane can provide a runway analysis for an additional cost.

¢ Shipment and storage: Unless otherwise noted equipment is rated for indoor use. Exposure to outdoor
elements can and will cause damage to the equipment, electrical components, paint surfaces, and void
the warranty.

¢ Mass Crane has not carried additional costs to store the equipment if the site is not ready. If the site is
not ready when the equipment is requested and previously scheduled it will be an additional cost to store
the equipment.

¢ Installation based on our non-union and non-prevailing wage rate crew during normal working hours
Monday-Friday 7:00-3:30 unless stated otherwise.

¢ Foundations not included, if foundations are required it will be an additional cost.

¢ Pricing based on one mobilization, if more than one mobilization is required it may be an additional cost.

¢ lf special on-site training is required for installers and technicians prior to working on site, it will be billed
on T&M basis.

¢ Performance and Payment Bond can be included for an additional cost of approximately $15.00 per
thousand

¢ Fire watch (if required) will be by Mass Crane inslallalion crew. If at: oulside fire watch Is required, It will
be an additional cost unless otherwise stated.

500-1 Potash Hill Road, Tyngsboro, MA 01879 e TELEPHONE 800-909-2299 « www.masscrane.com