and wiring used during work. Waldron will use this information to confirm cost validity of the
scope of work completed,
Detailed Review-Schedul
Methuen did not make a claim for schedule adjustment and as such no review was conducted.
Original Schedule Schedule Direct Schedule Schedule Claim
Adjustment claim impact Assessment Recommended
None none n/a 0 days
Conclusion
Waldron has reviewed all the available information, and has taken into consideration the factors
surrounding the issues in question. Waldron takes no exception to costs and schedule relief as
submitted.
Thus, Waldron recommends approving the Time and Material Not to Exceed $10,710.00 of the
claim as noted above and approving 0 days of schedule relief.
If you have any questions on the above, please don’t hesitate to contact me at 603-772-7153 x
105 or jsmith@waldron.com
Sincerely
Waldron Engineering & Construction, Inc.
Joreeey PB. Stehta
Jeremy P. Smith, P.B.
Project Manager