CHANGE ORDER
No. 1
PROJECT: WWITE Primary and Secondary Digester Coating
EXECUTED CONTRACT DATE: March 22, 2022
DATE OF ISSUANCE: July 7, 2022 EFFECTIVE DATE: Upon City Approval
OWNER: City of Nashua, NH
OWNER’s Purchase Order NO.: 170204
CONTRACTOR: John W. Egan Company, Inc
ENGINEER: WWTF Project Engineer
You are directed to make the following changes in the Contract Documents:
Description:
Additional work consisting of cleaning and coating surfaces of the following six (6) items:
1. Metal skirt at base of primary digester;
Exterior ladder on Dechlor Building;
Raw sewage pipe lateral in Wet Weather Facility;
Concrete deck repairs on CSO-002;
Seal exterior concrete foundation wall for Primary Digester and adjacent access building; and
Install new vinyl coated chain link fence on top of secondary digester
awn rwn
Justification:
This work is part of primary and secondary digester complex or, adjacent to the complex. Improvements to
these items is necessary to preserve the life and functionality of each.
Attachments: See attached John W. Egan cost proposal dated June 13, 2022
IFB1092-010522 WWTFE Primary and Secondary Digester Coating
Change Order #1