Engineering | Design | Planning | Gonsiruction Management
Nashua Transit Center Retrofit
Nashua, NH
INITIAL PROJECT SCOPING TASK DESCRIPTON
Prior to the commencement of any other work, the Consultant will meet with the City to review the
current and proposed layout of the site and building of the Transit Center. From this meeting, a specific
program will be developed consisting of all changes discussed. These changes will be incorporated
into a conceptual plan for the Transit Center and a detailed cost estimate will be developed for the
City’s review. The conceptual plan will include improvements to the Transit Center site, building,
and platform roof canopy. It is assumed that the plan will be developed using information currently
available, including but not limited to aerial imagery, GIS information, record drawings, and base
mapping previously prepared by the City.
The Consultant will meet with the City to review the conceptual plan and associated detailed cost
estimate and discuss the project budget for construction of these improvements, including engineering,
architectural and construction services.
This phase of the project will establish the scope of work for the remainder of the project.
Meetings and Deliverables:
The hours allocated to this task anticipate the following deliverables and meetings:
e Meeting #1: Site Design Meeting. GPI and SDA will observe the site and meet with the
City’s design team to identify a preferred direction on the building and site improvements.
« Site and Building Conceptual Plan. GPI will develop a conceptual site plan identifying site
improvements and SDA will develop a description of building improvements with materials
and quantities for costing.
e Cost Estimate. A detailed cost estimate will be developed based on the conceptual plan for
the site and building.
® Meeting #2: Cost Estimate Review Meeting. GPi and SDA will meet with the City’s design
team to review the costs and identify a preferred direction on the building and site
improvements. This will form the basis of the scope for the design phase of work.
e Conceptual Plan Revision. The conceptual plan will be revised, as necessary, to respond to
the cost estimate and the project funding.