Change Order Request
18101 — Nashua, NH - WWTF Primary Tank Subject: Change Order Request #2 EF-1 MCC two
Upgrade (DB Rates) speed starter adder
To Anthony Crespo Number: 18101-CO-002
Methuen Construction Revision Number: 0
Date: 9/19/2019
Price / Do Not
Electrical Installations, inc. .
RF! Reference No: 002
245 Charlotte Street D Valid:
Manchester, NH 03103 ays Valid: 5
603-520-0513
935-7862 (FAX)
chuck.fritz@eii-hg.com
Comments / Time Extension Request
Adder to change FVNR Starter for EF-1 to a 2 Speed, 2 Winding Starter 3/4 HP, with 2 relays, 2 Pilot Lights, 1
Elapsed Time Meter. ( HOA & High,Low,Stop Selector Switches are assumed to be
Remote to MCC), This unit is larger and will not fit in section #4. It will be placed in bottom of section #5.
Please note that pricing is based on
getting an immediate release without
having another round of Submittal
drawings. If the owner/engineer wants
an addition round of submittal drawings
add an additional $ 1500.00.
Details
4—Submittals/O&M's . 1.00
001 /Clerical/Office Clerical Labor $55.00 hrs 1.00 $55.00
00—Electrical Field . 0.00
002 Labor Onsite Electrician Labor $95.00 Hrs 0.00 $0.00
2—Instrumentation | Engineer 0.00
003 Field Labor Onsite Programmer Labor $110.00 Hrs 0.00 $0.00
004 5—Panel Shop Panel Shop Labor $65.00 oe 0.00 $0.00
Eaton Adder to 1.00
005 *EP*-Entire Project | change FVNR Material $3,000.00 LUMP -| $3,000.00
Starter for EF-1 SUM