  2. Finance Committee - Agenda - 11/6/2019 - P119

Finance Committee - Agenda - 11/6/2019 - P119

By dnadmin on Mon, 11/07/2022 - 13:02
Document Date
Fri, 11/01/2019 - 15:04
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 11/06/2019 - 00:00
Page Number
119
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__110620…

CHANGE ORDER

No. 3
PROJECT: Primary Tank Upgrade Project DATE OF ISSUANCE: _ 10/18/19
OWNER: City of Nashua, New Hampshire
229 Main Street
(Address) } OWNER’S Purchase Order No.

CONTRACTOR: Methuen Construction OWNER’s Project No. _IFB 0285-112918
CONTRACT FOR: Primary Tank Upgrade Project ENGINEER —_Wright-Pierce
ENGINEER’ s Project No. 13774

You are directed to make the following changes in the Contract Documents.

Description: See attached backup from Methuen Construction for various PCOs

Purpose of Change Order: Change in contract price for additional work and deductions from credited
work

Justification: See attached backup from Methuen Construction

Attachments: Methuen PCO NO. 3 Credit Request for Reducing Plant Water Pump Panel Feeder,
Methuen PCO NO. 4 MCC-2-Speed Starter for EF-1

CHANGE IN CONTRACT PRICE

Original Contract Price
3.629,340.00

CHANGE IN CONTRACT TIME

Original Contract Time
Subs. Completion: 6/18/20 / Final: 8/17/20

(days ar date)

Previous Change Orders
24,978.31

Net change from previous Change Orders

Subs. Completion: 0 / Final: 0
(days)

Contract Price prior to this Change Order
3,654,318.3]

Contract Time prior to this Change Order

Subs. Completion: 6/18/20 / Final: 8/17/20
{days or date)

Net Increase (Decrease) of this Change Order

3,483.78

Net Increase (decrease) this Change Order

Subs. Completion: 0 / Final: 0
(days}

Contract Price with all approved Change Orders

3,657,802.09

Contract Time with all Change Orders
Subs. Caimpletion: 6/18/20 / Final: 8/17/20

(days or date}

This document will become a supplement to the CONTRACT and all provisions will apply hereto. The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as

authorized by this Change Order.

Stipulated price and time adjustment includes all costs and time associated with the above described change.
Contractor waives all rights for additional time extension for said change. Contractor and Owner agree that

the price(s) and time adjustment(s) stated above are equitable and acceptable to both parties.

RECOMMENDED: APPROVED: APPROVED: APPROVED:
By: JEL ll By: By: By:
Engineer Owner Contractor NHDES
TE -2S- 14

Date Date Date Date