City of Nashua, Public Works Division
Board of Public Works Meeting Date: November 21, 2019
David L. Boucher, Superintendent
Wastewater Department
Wet Weather Influent Screening Upgrade — Construction Phase Services
To approve the contract with Wright Pierce of Thompson, ME in an amount not
to exceed $148,800 for construction administration services for the Wet Weather
Influent Screening Upgrade Project. Funding will be through: Department: 169-
Wastewater; Fund: Wastewater; Activity: Wet Weather Influent Screening
Upgrade.
Wright Pierce Engineering Cost Summary
The Wet Weather Influent Screening Upgrade Project was designed by Wright
Pierce and involves the replacement of the 2 existing screen and rakes along with
other upgrades to the Wet Weather Facility. The project was recently bid and
Waterline Industries Corporation was the low bidder. The project will require
construction management and Wright Pierce was asked to provide a scope and
cost proposal for this service.
Construction is estimated to last 11 months and Wright Pierce’s services will
include residential engineering and construction administration. Their cost
proposal of $148,800 is approximately 12% of the $1,237,677 construction costs.
These costs are considered reasonable since construction services are typically 10
to 12% of construction costs.