Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 12/4/2019 - P120

Finance Committee - Agenda - 12/4/2019 - P120

By dnadmin on Mon, 11/07/2022 - 13:01
Document Date
Wed, 11/27/2019 - 14:04
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 12/04/2019 - 00:00
Page Number
120
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__120420…

q

—s
par

‘

V

-
“

hb Design Services & Project Management of Downtown Riverfront Implementation

October 31, 2019

as the conceptual design of the entire project progresses. It will be important to integrate their
current lighting designs into any new work planned under this project. The current
understanding is that most if not all of the proposed Riverfront lighting will be built as part of
this project.

Product: Plans, details and images to illustrate the proposed conceptual improvements.

Lead Consultant: Lumen Design Studio
Support from: Fitzemeyer & Tocci, VHB
Estimated Duration: 8 weeks

1.7 Waytindin

The City is currently advancing a downtown wayfinding plan designed by others. For the
Riverfront project VHB will at most identify the conceptual recommended locations for
wayfinding signage during the conceptual stage, but actual wayfinding sign development will be
advanced in a later phase. For Phase 1 the wayfinding efforts will only include identifying
conceptual sign placement locations and potential general content.

Lead Consultant: VHB
Support from: Halvorson
Estimated Duration: 1 week, toward the end of Phase 1

1.8 Permitting Considerations

Permit applications will be prepared after Phase 2, but during Phase 1 the design team will be
cognizant of the potential permitting implications of every aspect of the design when important
design decisions are being made. Section 7 of the Riverfront Plan included a relatively
exhaustive evaluation of the permitting landscape for this project. As the design progresses,
however, VHB environmental specialists will advise the design team relative to any permitting
implications. In addition, The HL Turner Group will provide crucial input on any in-stream or
shoreline work that could potentially affect flood levels. If sub-projects are identified for
accelerated schedules it will be important to demonstrate that they have independent utility and
can be permitted on their own rather than waiting for the entire project to be permitted,

Lead Consultant: VHB
Support from: HL Turner, Halvorson
Estimated Duration: throughout Phase 1

1.9 Conceptual Cost Estimating
VHB will manage and assemble cost estimates for each of the project components from the

design team members in their respective disciplines. The HL Turner Group will provide costs for

12