Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 12/4/2019 - P113

Finance Committee - Agenda - 12/4/2019 - P113

By dnadmin on Mon, 11/07/2022 - 13:01
Document Date
Wed, 11/27/2019 - 14:04
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 12/04/2019 - 00:00
Page Number
113
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__120420…

=

V

hb

Design Services & Project Management of Downtown Riverfront Implementation
October 31, 2019

Following are descriptions of the various project components as they are currently understood
along with proposed roles and responsibilities of the applicable design team members for each
component. The below map provides a key to each of the primary numbered project
components. Estimated Duration: 16 weeks

1.4.1 - New Access at Factory St. Extension:

Task: Define the accessible route from Clock Tower Place to Factory Street Extension. This
may require ramps and/or creative use of the available space to satisfy ADA requirements.

Product: Provider up to two (2) design alternatives including plans, profiles, and sections as
appropriate to define the proposed improvements and to illustrate proposed grading.

Lead Project Team Consultant: VHB
Support from: HSI, Halvorson