amounts received from sales of surplus materials and equipment shall accrue to the Owner, and the Construction
Manager shall make provisions so that they can be obtained.
§ 6.9.2 Amounts that accrue to the Owner in accordance with the provisions of Section 6.9.1 shall be credited to the
Owner as a deduction from the Cost of the Work.
§ 6.10 Related Party Transactions
§ 6.10.1 For purposes of Section 6.10, the term “related party” shall mean a parent, subsidiary, affiliate or other
entity having common ownership or management with the Construction Manager; any entity in which any
stockholder in, or management employee of, the Construction Manager owns any interest in excess of ten percent in
the aggregate; or any person or entity which has the right to control the business or affairs of the Construction
Manager. The term “related party” includes any member of the immediate family of any person identified above.
§ 6.10.2 If any of the costs to be reimbursed arise from a transaction between the Construction Manager and a related
party, the Construction Manager shall notify the Owner of the specific nature of the contemplated transaction,
including the identity of the related party and the anticipated cost to be incurred, before any such transaction is
consummated or cost incurred. If the Owner, after such notification, authorizes the proposed transaction, then the
cost incurred shall be included as a cost to be reimbursed, and the Construction Manager shall procure the Work,
equipment, goods or service from the related party, as a Subcontractor, according to the terms of Sections 2.3.2.1,
2.3.2.2 and 2.3.2.3. If the Owner fails to authorize the transaction, the Construction Manager shall procure the Work,
equipment, goods or service from some person or entity other than a related party according to the terms of Sections
2.3.2.1, 2.3.2.2 and 2.3.2.3,
§ 6.11 Accounting Records
The Construction Manager shall keep full and detailed records and accounts related to the cost of the Work and
exercise such controls as may be necessary for proper financial management under this Contract and to substantiate
all costs incurred. The accounting and control systems shall be satisfactory to the Owner. The Owner and the
Owner’s auditors shall, during regular business hours and upon reasonable notice, be afforded access to, and shall be
permitted to audit and copy, the Construction Manager’s records and accounts, including complete documentation
supporting accounting entries, books, correspondence, instructions, drawings, receipts, subcontracts, Subcontractor’s
proposals, purchase orders, vouchers, memoranda and other data relating to this Contract. The Construction
Manager shall preserve these records for a period of three years after final payment, or for such longer period as may
be required by law.
ARTICLE 7 PAYMENTS FOR CONSTRUCTION PHASE SERVICES
§ 7.1 Progress Payments
§ 7.1.1 Based upon Applications for Payment submitted to the Architect by the Construction Manager and
Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the
Contract Sum to the Construction Manager as provided below and elsewhere in the Contract Documents.
§ 7.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of
the month, or as follows:
§ 7.1.3 Provided that an Application for Payment is received by the Architect not later than the «25th » day ofa
month, the Owner shall make payment of the certified amount to the Construction Manager not later than the «25th
» day of the «fo 1
date fixed above, payment shall be made by the Owner not later than «thi
receives the Application for Payment.
(Federal, state or local laws may require payment within a certain period of time.)
month. Ifan Application for Payment is received by the Architect after the application
(30° “} ) days after the Architect
§ 7.1.4 With each Application for Payment, the Construction Manager shall submit payrolls, petty cash accounts,
receipted invoices or invoices with check vouchers attached, and any other evidence required by the Owner or
Architect to demonstrate that cash disbursements already made by the Construction Manager on account of the Cost
of the Work equal or exceed progress payments already received by the Construction Manager, less that portion of
Page 11 of 16