§ 4.2 Payments
§ 4.2.1 Unless otherwise agreed, payments for services shall be made monthly in proportion to services performed.
§ 4.2.2 Payments are due and payable within 30 days of the Construction Manager’s invoice.
ARTICLE 5 COMPENSATION FOR CONSTRUCTION PHASE SERVICES
§ 5.1 For the Construction Manager’s performance of the Work as described in Section 2.3, the Owner shall pay the
Construction Manager the Contract Sum in current funds. The Contract Sum is the Cost of the Work as defined in
Section 6.1.1 plus the Construction Manager’s Fee.
§ 5.1.1 The Construction Manager’s Fee:
(State a lump sum, percentage of Cost of the Work or other provision for determining the Construction Manager's
Fee.)
§ 5.1.3 Limitations, if any, on a Subcontractor’s overhead and profit for increases in the cost of its portion of the
Work:
§ 5.1.4 Rental rates for Construction Manager-owned equipment shall not exceed «:» percent ( «
standard rate paid at the place of the Project.
%) of the
§ 5.1.5 Unit prices, if any:
(Identify and state the unit price; state the quantity limitations, if any, to which the unit price will be applicable.)
Item Units and Limitations Price per Unit ($0.00)
§ 5.2 Guaranteed Maximum Price
§ 5.2.1 The Construction Manager guarantees that the Contract Sum shall not exceed the Guaranteed Maximum
Price set forth in the Guaranteed Maximum Price Amendment, as it is amended from time to time, To the extent the
Cost of the Work exceeds the Guaranteed Maximum Price, the Construction Manager shall bear such costs in excess
of the Guaranteed Maximum Price without reimbursement or additional compensation from the Owner.
(Insert specific provisions if the Construction Manager is to participate in any savings.)
§ 5.2.2 The Guaranteed Maximum Price is subject to additions and deductions by Change Order as provided in the
Contract Documents and the Date of Substantial Completion shall be subject to adjustment as provided in the
Contract Documents.
§ 5.3 Changes in the Work
§ 5.3.1 The Owner may, without invalidating the Contract, order changes in the Work within the general scope of the
Contract consisting of additions, deletions or other revisions. The Owner shall issue such changes in writing. The
Architect may make minor changes in the Work as provided in Section 7.4 of AIA Document A201—2007, General
Conditions of the Contract for Construction. The Construction Manager shall be entitled to an equitable adjustment
in the Contract Time as a result of changes in the Work.
Page 7 of 16