Jim Donchess
Mayor e City of Nashua
To: Board of Aidermen
Filed With: Patricia Piecuch, City Clerk
From: Jim Donchess
Date: February 9, 2018
Re: Emergency PO Request — Emergency Contract with Crisp Contracting, LLC for an
amount not to exceed $55,000 to perform sewer repairs
Pursuant to 5-90 (G) of the NRO, | have authorized an Emergency Purchase Order to Crisp
Contracting, LLC for an amount not to exceed $55,000.
By way of background, the sewer pipe on Patten Court failed leaving many residents without sewer
service. The twelve inch concrete sewer pipe installed in 1890 has collapsed causing a blockage in
the pipe. The sewer serves the neighborhood consisting of about 9 dwelling units.
Patten Court is an older, narrow road with the buildings built between 1880 and 1890. A gas line
has been installed over the sewer pipe which may complicate this replacement project. This
request is in the amount not to exceed $55,000 to begin this emergency project.
Included is a copy of a memo from Steve Dookran, P.E., City Engineer explaining
the need for this emergency work, a copy of the quote from Crisp Contracting, LLC
and their insurance certificate.
Thank you,
CC: DPW Administration
229 Main Street » PO Box 2019 * Nashua, New Hampshire 03061-2019
603.589.3260 * fax 603.594.3450 * NashuaMayor@NashuaNH.gov
www.NashuaNH.gov