234
, Cost Qty;
Line No| Code Description Type / Rate / Hrs} Workers Ext
Conduit and pull
006 i mm ang PO" | Material $420.00 1.00 -| $420.00
x
007 Subcontractor Subcontractor $0.00 0.00 - $0.00
Breakout
Labor : $1,955.00
Gross Margin Percent @ 15%: $293.25
Material : $630.00
Gross Margin Percent @ 15%: $94.50
Total: $2,972.75
Reservation of Rights
This COR does not include any amount for impacts such as interference, disruptions, rescheduling, changes in the
sequence of work, delays and/or associated acceleration. We expressly reserve the right to submit our request for
any of these items.
Dated: 12/29/2017
Signed By: