Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 2/21/2018 - P232

Finance Committee - Agenda - 2/21/2018 - P232

By dnadmin on Mon, 11/07/2022 - 11:48
Document Date
Wed, 02/21/2018 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 02/21/2018 - 00:00
Page Number
232
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__022120…

T. Buck Construction, Inc.

249 Merrow Rd Auburn, ME 04210
207-783-6223 * FAX 207-783-3970

PROPOSAL 40

[Proposal Submitted to: Phone:
Wright-Pierce Fax:
|Street: Job Name

230 Commerce Way, Suite 302

Date 1/2/2018

Nashua Wastewater Treatment Facility Headworks Upgrade

[City, State & Zip Code: Job Location:

Portsmouth, NH 03801 Nashua NH
Engineer: Job Phone:
Andy Morrill
le hereby submit specifications and estimate for:
Provide labor, material and equipment for the following electrical work.
Relocate existing wiring in screenings room that is in non explosion proof boxes
Labor $ 1,955.00
Material $ 630.00
$ 2,585.00
15% O&P $ 387.75
$ 2,972.75
10% GC $ 258.50
SUB TOTAL $ 3,231.25 $ 3,231.25
Provide additional Fire Alarm parts
Labor $ 2,905.00
Material $ 3,701.00
$ 6,606.00
15% O&P $ 990.90
$ 7,596.90
10% GC $ 660.60
SUB TOTAL $ 8,257.50 $ 8,257.50
TOTAL $ 11,488.75
1) If this proposal is accepted T Buck Construction requests and additional 10 days be added to the contract time
e Propose hereby to furnish material and labor complete in accordance with above specifications, for the sum of:
ELEVEN THOUSAND FOUR HUNDRED & EIGHTY EIGHT DOLLARS
Ali material is guaranteed to be as specified, All work to be completed in a Authorized
workmanlike manner according to standard practices. Any alteration or Signature
deviation from above specifications invalving extra costs will be executed only Mark McPheters

upon written orders, and will become an exira charge over and above the
festimate. All agreements contigent upon strikes, accidents or delays beyond
four contro}. Owner to carry fire, tomado and other necessary insurance. Our
workers are fully covered by Workman's Compensation Insurance.

Note: This proposal may be withdrawn
by us if not accepted within 5 days

Acceptance of Proposal- the above prices, specifications and
a work as specified. Payment will be made as outlined above.
Date of acceptance

Signature

Page Image
Finance Committee - Agenda - 2/21/2018 - P232

Footer menu

  • Contact