  2. Finance Committee - Agenda - 2/21/2018 - P231

Finance Committee - Agenda - 2/21/2018 - P231

By dnadmin on Mon, 11/07/2022 - 11:48
Document Date
Wed, 02/21/2018 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 02/21/2018 - 00:00
Page Number
231
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__022120…

B-6.1

CHANGE ORDER
No. 9
PROJECT: _Headworks Upgrade DATE OF ISSUANCE: Upon City Approval
OWNER: City of Nashua
229 Main St, Nashua, NH 03062
(Address)
CONTRACTOR: T-Buck Consiruction, inc. OWNER’s Project No.

CONTRACT FOR: _Headworks Upgrade ENGINEER _ Wright-Pierce
ENGINEER’s Project No. 13089

You are directed to make the following changes in the Contract Documents.

Description: Refer to the Attachments.

Purpose of Change Order: Refer to the Attachments.

Justification: Refer to the Attachments.

_ Attachments: T Buck Construction Proposal #38 dated 10-20-17

CHANGE IN CONTRACT PRICE

Original Contract Price
$ _2,848,222.00

CHANGE IN CONTRACT TIME

Original Contract Time

455 days
(days er-date)

Previous Change Orders
$ 199,108.80

Net change from previous Change Orders
164 days

(days)

Contract Price prior to this Change Order
$ _3,047,326.80

Contract Time prior to this Change Order

619 days
(days or date)

Net Increase (Deerease) of this Change Order
$ 11,488.75

Net Increase (decrease) this Change Order

None
(days)

Contract Price with all approved Change Orders
$ 3,058,815.55

Contract Time with all Change Orders
619 days ( Final Completion 01/31/2018)

{days or date)

This document will become a supplement to the CONTRACT and all provisions will apply hereto. The
attached Contractor’s Revised Project Schedule reflects increases or decreases in Contract Time as

authorized by this Change Order.

Stipulated price and time adjustment includes all costs and time associated with the above described change.
Contractor waives all rights for additional time extension for said change. Contractor and Owner agree that

the price(s) and time adjustment(s) stated above are equitable and acceptable to both parties.

RECOMMENDEBR: APPROVED:
By: By:
ngineer Owner

L-18-2MH

APPROVED:
By: By:

APPROVED:

Contractor NHDES

Date Date

Date Date

13089A

Page Image
Finance Committee - Agenda - 2/21/2018 - P231