CHANGE ORDER
PROJECT: WWTTF SCADA Syst Upgrades
OWNER: City of Nashua
229 Main St., Nashua NH
(Address)
Electrical Installations, Inc
CONTRACTOR:
CONTRACT FOR: WWTF SCADA Syst Upgrades
No. 1
DATE OF ISSUANCE:
OWNER’s
Project No. IFB1094-100217
Weston & Sampson
ENGINEER Engineers, Inc
ENGINEER’s
Project No.
You are directed to make the following changes in the Contract Documents.
Description: SCADA System Integration Services
Purpose of Change Order: Revised Scope of Services
Attachments: (List documents supporting change) Electrical Installations, Inc Proposal 1781-P dated
October 27, 2017
CHANGE IN CONTRACT PRICE
Original Contract Price
$ 591,280.00
CHANGE IN CONTRACT TIME
Original Contract Time
From Notice to Procced
270 calendar days - Substantial] Completion
365 calendar days - Final Completion
(days or date)
Previous Change Orders
$ 0.00
Net change from previous Change Orders
none
(days)
Contract Price prior to this Change Order
$ 591,280.00
Contract Time prior to this Change Order
From Notice to Procced
270 calendar days - Substantial Completion
365 calendar days - Final Completion
(days or date)
Net Increase (Decrease) of this Change Order
$ 114,000.00
Net Increase (decrease) this Change Order
none
(days)
Contract Price with all approved Change Orders
$ 705,280.00
Contract Time with all Change Orders
From Notice to Procced
270 calendar days - Substantial Completion
365 calendar days - Final Completion
(days or date)
WWTF SCADA SYSTEM UPGRADES
CHANGE ORDER #1
Page 1 of 2