tiBeaulieu. Inc.
52 GAFFNEY STREET - NASHUA, NEW HAMPSHIRE 03060
(603) 883-5822 FAX# (603) 880-3106
www.chickbeaulieu.com
November 30, 2017
City of Nashua
P.O. Box 2019
Nashua, NH 03061 JOB SITE:
ATTENTION: Nick Caggiano 13 Stadium Drive
Nashua, NH 03062
Phone: 589-4759
EPDM ROOF PROPOSAL
1. General scope:
Install a new .060” fully adhered RPI EPDM roof system to the roof of the
building as described below.
2. Tear off:
° Strip off the existing roof system te the original decking. (Loose stone
only)
* Remove the existing drip edge. This will allow for carpentry repairs to
soffit and fascia areas.
e Cover the landscape around the perimeter of the building to help prevent
damage to the lawn and adjacent shrubbery. This process alse aids in the
collection of small pieces of roof material and nails.
3. Roof deck:
® Roof deck must be solid. The decking shall also be free from warpage,
bowing, delamination and separation from rafters.
® Inspect the roof deck for water damaged material.
Advise the owner of defective or deficient materials and the additional
cost of repair or replacement.
* Replace damaged boards to soffit area using a dry kiln board and not
pressure treated as specified. The pressure treated, unless allowed to dry
out, will not hold new paint.
4. Underlayments:
« Lay a %” isocyanurate foam base sheet over the existing deck/roof
materials.
« Fasten the base materials with 3” galvanized plates and screws long enough
to penetrate the existing roofing and decking a minimum of %”,