VH8-Vanasse Hangen Brustiin, inc City of Nashua, NH
2 Bedford Farms Dr. Suite 200 Breakdown of Tasks, Personnel Hours, and Cost
Bedford, NH 03110
BREAKDOWN OF TASKS - WATER STREET FINAL DESIGN
Total
QA/QC & Task Senior Sr, CADD | Admin. /CADD
Taaks EM Managers Engineer Engineer Tech, Tech Hours babonamioures
Final Plans (90%)
General Plan
Set Alignment 3 3 $285_
Label Curbing Geometry and Prowde Curbing Table 2 4 4 1a $1,150
Orainage Modifications and Notes 2 ij 4 4 it $1,365
Construction Notes 2 1 3 6 $930
Signing and Pavement Marking Plan 1 4 2 6 10 $1 230
Sign Summary Sheet 4 4 5 $715
Bridge Railing Modifications 2 4 §
Detail Sheei{s) 4 2 4 4 8 20 $2,880
Traffic Signal Mocifications (Water St al Main St) 1 2 4 6 13 $1775
106% Plans ind. Response to Comments 6 4 2 4 4 4 24 $3,660
Special Provisions 4 4 6 14 $2,590
Coordination with CM during the Contractor Procurement 4 4 4 12 $2,300
Projact Meetings f Corespondence/Coardination with City 12 12 24 $5.160
Subtotal 38 4 18 30 26 24 152 $24,040
——
TOTAL HOURS] 38 M 18 30 26 24 152
HOURLY RATES| _ $215.00 $215.00 $145.00 $95.00 $125.00 $85.00
LABOR CcOSsTS| $8,170 $7,370 $2,610 $2,950 $3,260 $2,040 $26,236
TOTAL LABOR = $26,230.00
VHB Water Street Final Design Fee 2022-05-19 ORAFT Date Prepared 6/9/2022