Summary
CHANGE IN CONTRACT PRICE:
Original Contract Price
$163,727
CHANGE IN CONTRACT TIMES:
Original Contract Times
Ready for final payment: September 10, 2014
Net changes from previous Change Orders
$620,184
Net change from previous Change Orders
Ready for final payment: December 15, 2017
Contract Price prior to this Change Order
$783,911
Contract Times prior to this Change Order
Ready for final payment: December 15, 2017
Net Increase (deerease} of this Change Order
$199,763
Net Increase (deerease} of this Change Order
Ready for final payment: December 15, 2018
Contract Price with all approved Change Orders
Contract Times with all approved Change Orders
$983,674 Ready for final payment: December 15, 2018
RECOMMENDED: ACCEPTED: APPROVED:
By: By:
Contractor Mayor Jim Donchess
(Authorized Signature) (Authorized Signature) Owner
(Authorized Signature)
Date: 2~ 20%] & Date: "
Date:
Change Order #4
Setback Barrier Wali 2 of 2