City of Nashua, Public Works Division
Board of Public Works Meeting Date: July 28, 2022
Daniel Hudson, P.E., City Engineer
Engineering Department
2022 Sidewalk Curb Ramps Replacement Project
To approve the construction contract for the 2022 Sidewalk Curb Ramps Replacement
Project with William P. Davis Excavation, LLC of Hampton, NH in an amount of
$380.220. Funding will be through Department: 160 Admin/Engineering; Fund: Bond;
Activity: Paving.
The 2022 Sidewalk Curb Ramp Replacement Project was developed to replace curb
ramps on planned paving streets in advance of paving work to expedite paving operations.
The project was advertised for bids on March 16" and was originally slated to reconstruct
approximately 60 sidewalk landings on Summer Street, Berkeley Street, and Harris Road,
including ADA compliance improvements, resetting curb, and reconstruction of concrete
or bituminous sidewalk to match the surrounding area. One bid was received on April 6"
from William P. Davis Excavation in an amount of $594,620.00.
Following bidding, we have elected to revise the proposed work to remove work on
Summer Street, Berkeley Street, and Harris Road and replace it with 20 curb ramps on
on East Dunstable Road and 14 landings on Manchester Street at a negotiated contract
value of $380,220.00.
William P. Davis is an established local contractor who has previously performed well
on projects at the Wastewater Treatment Plant and the Merrimack River Levee.