COST OR PRICE SUMMARY FORMAT FOR SUBAGREEMENTS UNDER NH SAG & SRF
Form Approved
DES 02/06
PART I- GENERAL
1. GRANTEE / LOANEE
City of Nashua, New Hampshire
2. GRANT/LOAN NO.
CS-300158-29
3. NAME OF CONTRACTOR OR SUBCONTRACTOR
Woodard & Curran, Inc.
4. DATE OF PROPOSAL
September 13, 2017
5. ADDRESS OF CONTRACTOR OR SUBCONTRACTOR (Include ZIP)
6. TYPE OF SERVICE TO BE FURNISHED
PART IIT- COST SUMMARY
HOURLY ESTIMATED
7. DIRECT LABOR (Specify labor categories) HOURS RATE COST TOTALS
Client Manager 20 $82.00 $1,640.00
Project Manager 81.5 $57.00 $4,646.00
Lead Project Engineer 148 $37.00 $5,476.00
Sr. Technical Advisor 16 $82.00 $1,312.00
SCADA Engineer 60 $45.00 $2,700.00
Sr. Electrical Engineer 12.5 $57.00 $713.00
Electrical Engineer 110 $37.00 $4,070.00
Staff Engineer 249 $27.00 $6,723.00
Sr. Structural Engineer 10 $57.00 $570.00
Structural Engineer 60 $37.00 $2,220.00
Cost Estimator 24 $49.00 $1,176.00
Technical Specialist HVAC 40 $46.00 $1,840.00
Project Specialist 40 $28.00 $1,120.00
$34,206.00
ESTIMATED
8. INDIRECT COSTS (Specify indirect cost pools) RATE X BASE = COST
2.02 $34,206.00 $69,096.00
INDIRECT COSTS TOTAL: $69,096.00
9. OTHER DIRECT COSTS
a. TRAVEL ESTIMATED
COST
(1) TRANSPORTATION $552.00
(2) PER DIEM
TRAVEL COSTS TOTAL: $552.00
b. EQUIPMENT, MATERIALS, SUPPLIES ESTIMATED
(Specify categories) QTY COST COST
EQUIPMENT SUBTOTAL:
c. SUBCONTRACTS ESTIMATED
COST
Geotechnical Services $3,200.00
SUBCONTRACTS SUBTOTAL:
d. OTHER (Specify categories) ESTIMATED
COST
OTHER SUBTOTAL:
e. OTHER DIRECT COSTS TOTAL: $3,752.00
10. TOTAL ESTIMATED COST $103,302.00
11. PROFIT $10,332.00
12. TOTAL PRICE $117,386.00
Page | of 2