City of Nashua, Public Works Division
Board of Public Works Meeting Date: April 26, 2018
David L. Boucher, Superintendent
Wastewater Department
Water Booster Station Upgrades ~- Bidding Phase Services — Amendment No. 2
To approve Amendment No. 2 in the amount of $8,200 to the contract with
Woodard & Curran for the Water Booster Station Upgrade. Funding will be
through: Department: 169 - Wastewater; Fund: SRF Loan; Activity: Water
Booster Station.
Woodard Curran Scope of Work and Fee.
The Nashua Wastewater Treatment Facility entered into a contract on March 3,
2017 with the engineering firm of Woodard & Curran to provide professional
services in the amount of $105,600. This service included designing an above
ground water booster station to replace the original 1988 underground (vault)
booster station.
Amendment No. 1 to the contract, in the amount of $3,586 was for
Geotechnical Services to evaluate soil conditions in the project area. The
amendment increased the original contract cost to $109,186.
Amendment No. 2 to the contract, in the amount of $8,200 is for Bidding Phase
Services, which was not included in the original contract. The amendment will
increase the cost of the original contract to $117,386.