es ‘a3
qo. W.COLE
ENGINEERING, INC.
COST ESTIMATE
PROJECT NAME:
Heritage Rail Trail Connection to Mine Falls Park
CLIENT: Hoyle, Tanner & Associates
PROJECT NO: 18-0204
DATE: 2/21/2018
PROJECT MANAGER: A. Michaud
ESTIMATED SUBTOTAL §$ §,225
ESTIMATED TOTAL WITH 10% CONTINGENCY $ 5,748
TASK Miles | Travel | Time On| Hourly | Trips/v| Mileag | No. of Unit TEST TOTAL] COST TOTAL FIELD | SUBTOTAL
(RND) | Time site Rate | isits * e Tests *| Costtest PERTRIP| TRIPS TOTAL | (including
({RND) COST travel)
FIELD SERVICES
Concrete Testing - Half Day {includes cylinders) 28 1 4 $ 58 6 $ 0.54 30 $ 15.00] $ 450.00 | $ 731$ 439] 3 1,392]$ 2,281
Soil & Aggregate Testing - Half Day (includes gauge) 28 1 8 $ 658 3 $ 0.54 40 $ 7.00] $ 280.00 | $ 731 $ 219]$ 1392/5 1,891
Grain Size Analyisis 2 $3 95.00] 5 190.00 $ 190
Moisture Density Relationship 2 $ 125.00 | $ 250,00 $ 250
Sample Pickups 28 1 0.25 $58 7 $ 0.54 $ 731 $ 512 | $ 102 | $ 613
* ASSUMED VALUES
ATTACHMENT A-1