=" 18-0204 M
==SWCOLE February 21, 2018
lao VV o Ne
OWA EN GINEERINGING.
Concrete
e Perform tests for air and mix temperatures, slump and air content during
placement
e Cast strength test specimens and test for compressive strength
We will provide reports of field observations and testing directly to the client, with copies
forwarded to the Engineer and Owner or as requested. The project will be serviced
from our Manchester, New Hampshire office. Our project manager will be Andrew
Michaud he can be reached at 603-716-2111 or amichaud@swcole.com.
REPORTS
We will provide reports of field observations and testing on a daily basis directly to the
client, with copies forwarded to the engineer and building official as requested by the
client. Test reports will be transmitted in a timely fashion. Delivery of our reports will be
done via email (in .pdf format).
It should be understood by the client and others providing services on this project that
the scope of observations and testing performed by S.W.COLE are for the use of our
client and are not a substitute for the quality control requirements of the contractor and
others.
We understand S.W.COLE does not have the authority to accept or approve any work
performed by contractor(s), and that the general contractor has full responsibility for the
project including means and methods, schedule, safety, completeness, and quality in
accordance with the project contract specifications.
SCHEDULE
We anticipate that our services will be needed on a part time basis as scheduled by the
client or their designated representative. Richard Smith is responsible for field
scheduling. He can be reached at 603-716-2111 or rsmith@swcole.com. We request
24 hours notice for scheduling of field services.