176
NHDOT FUNDING SUMMARY
The following is a summary of the total estimated project costs to date:
Preliminary Engineering (PE)
Feasibility Study Phase $36,547.20 $9,136.80 $45,684.00
Preliminary Design Phase $29,456.00 $7,364.00 $36,820.00
Final Design Phase $18,422.40 $4,605.60 $23,028.00
Bid Phase $3,464.00 $866.00 $4,330.00
PE Total $87,889.60 $21,972.40 $109,862.00
ROW Total
Construction (CON)
Construction Cost (EST.) $274,240.00 $68,560.00 $342,800.00
Construction Engineering $66,873.60 $16,718.40 $83,592.00
TOTAL $429,003.20 $107,250.80 $536,254.00