Stormwater Pollution Prevention Plan (SWPPP)
Video Inspection
Traffic Control Plan
Invasive Species Management Plan
Prefabricated Steel Pedestrian Bridge Erection Plan
Certificate of Compliance (13 Items)
Product Data (13 Items)
Concrete Mix Designs
Asphalt Mix Designs
00000000 0
A-8. Review and approval of shop drawings and/or working drawings does not extend to the
means and methods of construction nor to safety precautions and programs of the
Contractor.
A-9. Hoyle, Tanner will arrange for a construction testing agency to perform material testing
of cast-in-place concrete, precast concrete elements, and soil backfill compaction. All
soil materials will be tested by personnel certified in sampling and testing by the
NorthEast Transportation Training & Certification Program (NETTCP). All concrete
materials will be tested by personnel certified by the NETTCP, the American Concrete
Institute or the Prestressed Concrete Institute as appropriate. We intend to use S.W.
Cole, Inc. from Manchester, NH for these services. An estimate of the cost for these
services is included in our estimate of fee and reimbursable expenses indicated in Exhibit
C.
A-10. Measurement and documentation of quantities will include the following tasks:
o A Quantity and Record Book (2 separate documents) shall be prepared in advance
of construction for use in the field by the RPR.
o The RPR will measure all items constructed on a daily basis and record them in a
field book.
o The field measurements will then be cross-referenced into a Quantity Book and
brought forward to a summary spreadsheet for each pay period.
o Each pay requisition submitted by the contractor will be reviewed versus the
summary spreadsheet.
o The RPR shall track ongoing and future construction expenditures by completing
an “Engineer's Estimate of Balances and Excesses” as the project approaches 25%,
50%, 75% and 90% complete.
o ARecord Book of Quantities will be prepared by the RPR, which includes individual
item summary pages, substantiating documents and calculations pages.
o The Project Manager will visit the project site on a monthly basis to check the
Quantity Book, Field Measurements and Pay Requisitions.
o Itis assumed the RPR will be allowed to utilize the contractor's survey equipment
to complete earthwork measurements. It is further assumed that the contractor
will provide a rod man, if needed, to assist with these efforts.
A-11. Advertising the project for bidding will occur in the spring of 2018.
A-12, The Contractor's construction contract will have a duration of 170 calendar days (24
weeks) to achieve substantial completion and an additional 30 days (which equates to a
project total of 200 calendar days or 28 weeks) to achieve final completion starting during
the summer or fall of 2018 with all on-site work occurring between 7 AM to 7 PM, Monday
through Friday. The first 12 weeks of the construction contract duration are expected to