Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 5/16/2018 - P150

Finance Committee - Agenda - 5/16/2018 - P150

By dnadmin on Mon, 11/07/2022 - 11:40
Document Date
Wed, 05/16/2018 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 05/16/2018 - 00:00
Page Number
150
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__051620…

care. Any approval by the City of any products or services furnished or used by Professional
Engineer shall not in any way relieve Professional Engineer of the responsibility for professional
and technical accuracy and adequacy of its work. City review, approval, or acceptance of, or
payment for any of Professional Engineer's work under this contract shall not operate as a waiver
of any of the City's rights or causes of action under this contract, and Professional Engineer shall
be and remain liable in accordance with the terms of the contract and applicable law.

Professional Engineer shall furnish competent and skilled personnel to perform the work under
this contract. The City reserves the right tc approve key personnel assigned by Professional
Engineer to perform work under this contract. Approved key personnel shall not be taken off of
the project by Professional Engineer without the prior written approval of the City, except in the
event of termination of employment. Professional Engineer shall, if requested to do so by the City,
remove from the job any personnel whom the City determines to be incompetent, dishonest, or
uncooperative.

4. Ciry REPRESENTATIVE. The City may designate a City representative for this contract.
If designated, all notices, project materials, requests by Professional Engincer, and any other
communication about the contract shall be addressed or be delivered to the City Representative.

5. CHANGES TO SCOPE OF WORK. The City may, at any time, by written order, make
changes to the general scope, character, or cost of this contract and in the services or work to be
performed, either increasing or decreasing the scope, character, or cost of Professional Engineer's
performance under the contract. Professional Engineer shall provide to the City within 10 calendar
days, a written proposal for accomplishing the change. The proposal for a change shall provide
enough detail, including personnel hours for each sub-task and cost breakdowns of tasks, for the
City to be able to adequately analyze the proposal. The City will then determine in writing if
Professional Engineer should proceed with any or all of the proposed change. If the change causes
an increase or a decrease in Professional Engineer's cost or time required for performance of the
contract as a whole, an equitable adjustment shall be made and the contract accordingly modified
in writing. Any claim of Professional Engineer for adjustment under this clause shall be asserted
in writing within 30 days of the date the City notified Professional Engineer of the change.

When Professional Engineer seeks changes, Professional Engineer shall, before any work
commences, estimate their effect on the cost of the contract and on its schedule and notify the City
in writing of the estimate. The proposal for a change shall provide enough detail, including
personnel hours for each sub-task and cost breakdowns of tasks, for the City to be able to
adequately analyze the proposal. The City will then determine in writing if Professional Engineer
should proceed with any or all of the proposed change.

Except as provided in this paragraph, Professional Engineer shall implement no change unless the
City in writing approves the change. Unless otherwise agreed to in writing, the provisions of this
contract shall apply to all changes. The City may provide verbal approval of a change when the
City, in its sole discretion, determines that time is critical or public health and safety are of concern.
Any verbal approval shall be confirmed in writing as soon as practicable. Any change undertaken
without prior City approval shall not be compensated and is, at the City's election, sufficient reason
for contract termination.

6. CITY COOPERATION. The City agrees that its personnel will cooperate with Professional

Engineer in the performance of its work under this contract and that such personnel will be
available to Professional Engineer for consultation at reasonable times and after being given