Nashua Fire Rescue SAMPLE
RedNMX implementation Plan (Based on sample of modules)
NFR reviews map layers lock good Month 3
NFR approves and goes live with GIS Month 3
Mobile Dispatch
Verify Mobile devices are available. Month 3
Get connecied via Logiviein io the windows devices Month 3
Get the switch installed on the Server Month 3
Get Mobile Dispatch setup on MDTs Month 3
Install mapping and AVL Month 3
Finalize Mobile Dispatch Month 3
Go live with Mobile Dispatch Month 3
Mobile Inspections
Verify Mobile devices are available. Month 3
Get connected via LogMeln to the windows devices Month 3
Get local DB installed on MDTs Month 3
Get Mobile Inspections on MDTs Month 3
Get custom inspection form configured for mobile Month 3
Test Faxing and uploading of inspections documents Month 3
Finalize Mobile Inspections Month 3
Go live with Mobile Inspections Month 3
Bulletin Board Module
Alpine installs basic Bulletin Board Month 3
NFR send us what they would like Month 3
Alpine builds Bulletin Board application Month 3
NFR sets up hardware Month 3
NFR provides remote access to Hardware Month 3
Alpine installs Bulletin Board application on hardware Month 3
NFR approves Bulletin Board Application Month 3
Go live with Bulletin Board Month 3
Responder App
Alpine Installs services on NFR Server Month 4
Alpine sets up link for Responder app Month 4
Show how to configure members for Responder Month 4
NFR Sends out link to selected members Month 4
NFR tests Responder module Month 4
NFR approves module Month 4
Go live with Responder App Month 4