Finance Committee - Agenda - 6/6/2018 - P225

By dnadmin on Mon, 11/07/2022 - 11:37
Document Date
Wed, 06/06/2018 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 06/06/2018 - 00:00
Page Number
225
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__060620…

4. CITY OF NASHUA REPRESENTATIVE The City of Nashua may designate a City of Nashua
representative for this contract. If designated, all notices, project materials, requests by
Independent Contractor, and any other communication about the contract shall be addressed or be
delivered to the City of Nashua Representative.

5. CHANGES TO SCOPE OF WORK The City of Nashua may, at any time, by written order, make
changes to the general scope, character, or cost of this contract and in the services or work to be
performed, either increasing or decreasing the scope, character, or cost of Independent
Contractor's performance under the contract. Independent Contractor shall provide to the City of
Nashua within 10 calendar days, a written proposal for accomplishing the change. The proposal
for a change shall provide enough detail, including personnel hours for each sub-task and cost
breakdowns of tasks, for the City of Nashua to be able to adequately analyze the proposal. The
City of Nashua will then determine in writing if Independent Contractor should proceed with any
or all of the proposed change. If the change causes an increase or a decrease in Independent
Contractor's cost or time required for performance of the contract as a whole, an equitable
adjustment shall be made and the contract accordingly modified in writing. Any claim of
Independent Contractor for adjustment under this clause shall be asserted in writing within 30
days of the date the City of Nashua notified Independent Contractor of the change.

When Independent Contractor seeks changes, Independent Contractor shall, before any work
commences, estimate their effect on the cost of the contract and on its schedule and notify the
City of Nashua in writing of the estimate. The proposal for a change shall provide enough detail,
including personnel hours for each sub-task and cost breakdowns of tasks, for the City of Nashua
to be able to adequately analyze the proposal. The City of Nashua will then determine in writing
if Independent Contractor should proceed with any or all of the proposed change.

Except as provided in this paragraph, Independent Contractor shall implement no change unless
the City of Nashua in writing approves the change. Unless otherwise agreed to in writing, the
provisions of this contract shall apply to all changes. The City of Nashua may provide verbal
approval of a change when the City of Nashua, in its sole discretion, determines that time is
critical or public health and safety are of concern. Any verbal approval shall be confirmed in
writing as soon as practicable. Any change undertaken without prior City of Nashua approval
shall not be compensated and is, at the City of Nashua's election, sufficient reason for contract
termination.

6. CITY OF NASHUA COOPERATION ‘The City of Nashua agrees that its personnel will cooperate
with Independent Contractor in the performance of its work under this contract and that such
personnel will be available to Independent Contractor for consultation at reasonable times and
after being given sufficient advance notice that will prevent conflict with their other
responsibilities. The City of Nashua also agrees to provide Independent Contractor with access to
City of Nashua records in a reasonable time and manner and to schedule items that require action
by the Board of Public Works and Finance Committee in a timely manner. The City of Nashua
and Independent Contractor also agree to attend all meetings called by the City of Nashua or
Independent Contractor to discuss the work under the Contract, and that Independent Contractor
may elect to conduct and record such meetings and shall later distribute prepared minutes of the
meeting to the City of Nashua.

7. DISCOVERY OF CONFLICTS, ERRORS, OMISSIONS, AMBIGUITIES, OR DISCREPANCIES
Independent Contractor warrants that it has examined all contract documents, has brought all
conflicts, errors, discrepancies, and ambiguities to the attention of the City of Nashua in writing,
and has concluded that the City of Nashua’s resolution of each matter is satisfactory to
Independent Contractor. All future questions Independent Contractor may have conceming
interpretation or clarification of this contract shall be submitted in writing to the City of Nashua
within 10 calendar days of their arising. The writing shall state clearly and in full detail the basis
for Independent Contractor's question or position. The City of Nashua representative shall render

GC3 of 11

Page Image
Finance Committee - Agenda - 6/6/2018 - P225

Footer menu