May 30th, 2018
PROJECT NAME; Marshail st
PLAN DATED: May 24”
ADDENDUM RECEIVED:
ENGINEER/ ARCHITECT NAME: Pete Kohalmi, PE City of Nashua
Deputy City Engineer
INCLUSION, EXCLUSION AND CLARIFICATIONS
OVERALL SCOPE OF WORK FOR DEMO:
Equipment mobilization.
Supervision
Remove and replace4 CB’s.
Remove and replace Concrete curb with Granite Curbing.
Adjust frame and covers for new grades and pavement.
Loam and seed disturbed areas.
4 Catch Basins @ $4,500 each = $18,000
200 If curb removal and rest with Granite $40 If = $8,000
Remove and reset existing curb 20 If @ $20 = $400
Loam and seed 20 cy @ $22 per cy= $440
Adjust frame and covers 3 @ $500 each = $1,500
Supervision/Admin/Traffic control. Lump sum = $4,200
EXCLUSION:
Hazardous or contaminated materials.
Permits and additional bonds.
Uniformed officer traffic detail.
Removal/ relocate existing utilities.
Utility pole bracing or holding.