City of Nashua, Public Works Division
Board of Public Works Meeting Date: May 31, 2018
Stephen Dookran, P.E., City Engineer
Engineering Department
Marshall St Drainage Improvements
To approve a contract with Thibeault Corp. of Manchester, NH for the amount not to
exceed $35,000 for drainage improvements on Marshall St. Funding will be through
Department: 169 Wastewater; Fund: Wastewater; Activity: CSO Flooding.
Currently drainage work on Marshall St is being performed by Thibeault Corp. in
relation to the housing development at 22 Marshall Street. DPW would like to make
additional drainage improvements that include replacing deteriorated catch basins and
regrading of the street to reduce existing puddles.
Using Thibeault to do the additional drainage work is the best option at this time since
they are already mobilized for that type of work. They are also performing pipe
replacement on Marshall St for Pennichuck Water Works.
It is also important to note that the overall drainage improvements on Marshall St will
result in additional sewer separation and are therefore a benefit to the City’s CSO
program.