SECTION 413
Method of Measurement
4.1 Hot-poured crack sealant will be measured by the pound of material incorporated in the work.
Basis of Payment
5.1 The accepted quantity of hot-poured crack sealant will be paid for at the contract unit price per pound, complete in place.
5.2 Cleaning and routing will be subsidiary.
Pay item and unit:
413.1 Hot-Poured Crack Sealant Pound
413.2 Hot-Poured Crack Sealant (Low Modulus) Pound