Finance Committee - Agenda - 6/6/2018 - P116

By dnadmin on Mon, 11/07/2022 - 11:36
Document Date
Wed, 06/06/2018 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 06/06/2018 - 00:00
Page Number
116
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__060620…

To:

From:

Re:

D. Motion:

Discussion:

City of Nashua, Public Works Division
Board of Public Works Meeting Date: May 31, 2018

Stephen Dookran, P,.E., City Engineer
Engineering Department

2018 Sewer Replacement — Kinsley St
Construction

To approve the construction contract for the 2018 Sewer Replacement — Kinsley St
project to Newport Construction of Nashua, NH in an amount not to exceed $1,139,300.
Funding will be through: Department: 169 Wastewater; Fund: Wastewater; Activity:
Sewer Rehab.

This contract is for sewer improvements on Kinsley St in advance of street paving later
this year. From Elm St to Walnut St, the contract will replace 170 feet of 12 inch
unreinforced concrete main and 310 feet of 15 inch clay main, both dating back before
1900. From Walnut St to Woodward St, deteriorated catch basins and laterals will be
replaced as needed in advance of lining the sewer main in a separate contract by others.
Coordination issues with abutters and school activities may impact the construction
schedule.

Two bids were received on May 22 as follows:

Newport Construction of Nashua, NH $1,139,300.00
N. Granese & Sons of Salem, MA $1,725,000.00

The low bidder, Newport Construction of Nashua, NH has successfully completed
sewer work of this type for other municipalities.