Skip to main content

Main navigation

  • Documents
  • Search

User account menu

  • Log in
Home
Nashua City Data

Breadcrumb

  1. Home
  2. Finance Committee - Agenda - 6/6/2018 - P57

Finance Committee - Agenda - 6/6/2018 - P57

By dnadmin on Mon, 11/07/2022 - 11:36
Document Date
Wed, 06/06/2018 - 00:00
Meeting Description
Finance Committee
Document Type
Agenda
Meeting Date
Wed, 06/06/2018 - 00:00
Page Number
57
Image URL
https://nashuameetingsstorage.blob.core.windows.net/nm-docs-pages/fin_a__060620…

3/15/2018

@

MOTOROLA
SOLUTIONS

. Motorola

ST Ties

Provide an elevated antenna mounting location, and adequate feed-line O

routing and support.

Install line (not greater than 100 feet in length) and antenna system A O

(connectors, coax grounding kit, antenna, and surge protection).

Install RF local control stations identified in the equipment list. O

Perform control station programming. O

Deliverable: Control station equipment installation completed.

Functional Acceptance Testing

Verify the operational functionality and features of the solution supplied by QO

Motorola Solutions, as contracted.

Witness the functional testing. O

Document all issues that arise during the acceptance tests. O

If any major task for the system as contractually described fails during the

Customer acceptance testing or beneficial use, repeat that particular task O

after Motorola Solutions determines that corrective action has been taken.

Resolve any minor task failures before Final System Acceptance. O

Document the results of the acceptance tests and present for review. O

Review and approve final acceptance test results. O
Deliverable: Completion of functional testing and approval by Customer.

Finalize Documentation and System: Acceptance

Provide manufacturer's installation material, part list and other related O

material to Customer upon project completion,

Provide an electronic as-built system manual on CD or other Customer

preferred electronic media. The documentation will include the following: ©

Site Block Diagrams. « Site Floor Plans. ¢ Site Equipment Rack

Configurations. * Antenna Network Drawings for RF Sites (where

applicable). * ATP Test Checklists. « Functional Acceptance Test Plan Test O

Sheets and Results. « Equipment Inventory List. * Console Programming

Template (where applicable). * Maintenance Manuals (where applicable). ¢

Technical Service Manuals (where applicable). Drawings will be delivered in

Adobe PDF format.

Receive and approve documentation. O

Execute Final Project Acceptance. VY

Deliverable: All required documents are provided and approved. Final Project Acceptance.

PPPOE RTE EERE REET TEER ee ee COOP PAPEETE RE ERT aT RTE

Use or disclosure of this proposal is subject
to the restrictions on the disclosure page.

Page 22

Page Image
Finance Committee - Agenda - 6/6/2018 - P57

Footer menu

  • Contact