City of Nashua
Communications Division
Attention; Mr. William Mansfield
Radio Systems Manager
Reference: Replace 1- 2.5 ton Mitsubishi ductless split system at the old Signal Fire Station /
911 call center Lake Street.
Dear Bill,
We are pleased to submit for your consideration our price for the above referenced project.
Included in this price is the following.
Reclaim R-22 gas from existing system.
Remove old ductless split system and dispose.
Install new Mitsubishi cuctless split system.
Drain Piping
New ACR piping.
Inter connecting wire.
Crane
Start and Test proper operation of new system.
Our price for the above referenced project is $9,450.00 (nine thousand four hundred fifty eight
dollars).
If you have any questions or concerns please don't hesitate to call.
Respectfully Submitted,
AAA E Service Co,
Shawn Hersey
Project Sales Engineer
{a
Providing HVAC/R Services Since 1748