Finance Committee - 6/6/2018 Page 7
Alderwoman Kelly
Okay, thank you.
MOTION CARRIED
From: Dan Kooken, Purchasing Manager
Re: Unleaded Fuel Contract (Value Estimated $421,434)
MOTION BY ALDERWOMAN KELLY TO ACCEPT, PLACE ON FILE AND AWARD THE CONTRACT TO
DENNIS K. BURKE, INC., IN AN ESTIMATED AMOUNT OF $421,434. SOURCE OF FUNDING IS
DEPARTMENT 186, TRANSPORTATION; VARIOUS DEPARTMENT’S GENERAL FUNDS
MOTION CARRIED
From: Dan Kooken, Purchasing Manager
Re: 2018 Sewer Replacement — Kinsley Street (Value: $1,139,300)
MOTION BY ALDERWOMAN KELLY TO ACCEPT, PLACE ON FILE AND, CONTINGENT UPON BOARD
OF ALDERMEN APPROVAL, AWARD THE CONTRACT TO NEWPORT CONSTRUCTION CORPORATION
IN THE AMOUNT OF $1,139,300. FUNDS ARE AVAILABLE IN DEPARTMENT 169, WASTEWATER
ON THE QUESTION
Alderman Laws
| was just wondering generally when this Kinsley Street project should be, it is one of the streets that | get
questions about most often.
Mr. Dookran
Yes Kinsley Street is an all-paving program scheduled to be paved this year. However, there is all this work to
be done, as you might have seen there is natural gas work, Liberty Utilities is out there and they have done
quite a bit of work. They still have a lot left. The next step is for us to get the sewer work done and our hope is
to get it all done prior to getting the street paved this year. If this runs over then it will have to be next year but
we are shooting for completing the paving this year.
MOTION CARRIED
From: Dan Kooken, Purchasing Manager
Re: 2018 Asphalt Testing (Value: $43,875)
MOTION BY ALDERWOMAN KELLY TO ACCEPT, PLACE ON FILE AND AWARD THE CONTRACT TO
S.W. COLE ENGINEERING, INC., IN THE AMOUNT OF $43,875. SOURCE OF FUNDING IS
DEPARTMENT 161, STREET; GENERAL AND TRUST FUNDS
ON THE QUESTION
Mayor Donchess
Since | think there is quite a bit of interest in our paving program, maybe Mr. Dookran you could give an
explanation of what this testing is.