Electric Utility, Morton International, Army Research Lab Watertown, and Public
Services Colorado. Set up air modeling for Arco Channelview.
Emissions Testing
PPL Landfill Gas Recovery (now EPP) — Various Locations (Project
Manager 2000 - Present)
Worked with PPL to test engines and flares burring landfill gas. Optimized
engine operation to maximize power generation and minimum emissions. Flare
testing was to maximize methane production from landfill to minimize
supplemental fuel use.
BFI Gas Recovery Services (now Fortistar) — Various Locations (Project
Manager 2000 - Present)
Worked with BFI to test engines and flares burring landfill gas. Optimized engine
operation to maximize power generation and minimum emissions. Flare testing
was to maximize methane production from landfill to minimize supplemental fuel
use.
Newington Power Generation Station — Initial Compliance/Performance
Testing (Key Operator: 2002)
Part of the air emission testing team to demonstrate compliance with the state
operating permit and the manufacture performance guarantee. Performed the
testing while the plant was operating on natural gas then repeated the testing
while firing oil. Parameters monitored were NOx, CO, Oz, PMio, Opacity, SOz2,
VOC, and NH3.
Newington Power Generation Station — Annual Compliance Testing (Field
Team Leader: 2003 - 2007)
Mr. Gill served as Field Team Leader. TRC conducted compliance emissions
testing on the unit to demonstrate compliance with the state permit emission
limits (CO, NOx, SOz, and NHs) from the New Hampshire Air Resource Division
(NHARD). Responsible for the analytical instruments used during all the gas
RATAs. The EPA test methods utilized during the program are found in the 40
CFR Part 60, Appendix A.
Mt. Tom Power Generation Station - RATAs and Mercury Testing (Field
Team Leader: 2006 - 2011)
Worked on the mercury monitoring system by collecting samples from the
calibrator to verify its output calibration concentration. Performed several gas
RATAs to demonstrate the mercury monitoring system was functioning properly.
Also was the field team lead in several other gas and flow RATA testing
programs.
DEA (o METI}