To:
From:
Re:
E. Motion:
Attachments:
Discussion:
City of Nashua, Public Works Division
Board of Public Works Meeting Date: June 28, 2018
David Boucher, Superintendent
Wastewater Department
Waste Water Facility HVAC Upgrades
To approve Change Order #4 to the HVAC Upgrades contract with Monadnock Building
Company in the amount of $17,940.40. Funding will be through: Department: 169 -
Wastewater; Fund: Wastewater; Activity: AC & Air Handling.
Change Order #4 Backup
The contract with Monadnock Builders to rebuild the HVAC system in the Control and
Grit Buildings at the Wastewater Treatment Facility is currently at a contract value of
$951,055.10.
Change Order #4, in the amount of $17,940.40, is for additional duct smoke detectors on
two of the larger heating units, which were required as a result of an inspection by the
City Building Inspector. This change order increases the contract value to $968,995.50.