CLD | Fuss & O'Neill Cost Estimate
CITY OF NASHUA
CANAL ST BRIDGE - CONCRETE REPAIRS
ESTIMATED WORK HOURS
Project | QA/QC | Project Tech. Total
Manager} Sr. Eng. |Engineer]Engineer| Tech. | Typist Hours
Prepare Construction Details 1 2 6 12 16 37
Field Inspection 6 6 6 18
Prepare NHDES PBN 1 1 4 16 12 34
Prepare Quantities and Estimate 1 2 4 7
Prepare Bid Form and Special Provisions 1 3 8 12
Bidding Assistance
Contractor Inquiries & Addenda 1 1 2 2 1 7
Shop Drawing Review 1 2 4 4 1]
Review Bids, Quantities & Contractor 1 1 2 2 6
Prepare Contracts, NOA, NTP, Insurance & Bond 1 > 4 7
Review
Construction Inspection/Administration (6 site visits) 1 8 24 33
Project Administration & Coordination (assume 1 4 > > g
meeting)
Hour Subtotal:| 12 13 44 70 34 7 180
ESTIMATED ENGINEERING COSTS
Work Estimated Estimated
Hours Hourly Rate Costs
Project Manager 12 $ 50.00 $ 600
QC/QA & Senior Engineer 13 52.18 678
Project Engineer 44 50.00 2,200
Engineer 70 35.84 2,509
Technician 34 25.99 884
Technical Typist 7 22.05 154
180 Total Direct Labor $ 7,025
Indirect Costs @ 1.7. 11,943
Subtotal $ 18,968
Fixed Fee $ 1,897
Subtotal $ 20,865
Direct Costs $ 190
CLD Total Estimated Cost: $ 21,055
Materials Testing $ 10,000
TOTAL ESTIMATED COST: 31,055,
20160362.000 -l- 6/2018