CANAL ST BRIDGE - WEEP HOLE INSTALLATION
ESTIMATED WORK HOURS
Project | QA/QC | Project Tech. Total
Manager] Sr. Eng. | Engineer]Engineer| Tech. | Typist | Hours
Prepare Construction Details 1 1 4 6 12
Prepare Quantities and Estimate 1 2 4 7
Prepare Bid Form and Special Provisions 1 2 6 9
Bidding Assistance
Contractor Inquiries & Addenda 1 2 2 1 6
Review Bids, Quantities & Contractor 1 1 2 2 6
Prepare Contracts, NOA, NTP, Insurance & Bond 1 2 4 7
Review
Construction Inspection/Administration (3 site visits) 4 12 16
Weep Hole Monitoring (5 Site Vists and Reports) 1 10 11
Project Administration & Coordination (assume 1 4 2 > 8
meeting)
Hour Subtetal: 8 7 20 34 6 7 82
Project Manager
QC/QA & Senior Engineer
Project Engineer
Engineer
Technician
Technical Typist
20160362.000
ESTIMATED ENGINEERING COSTS
Work Estimated Estimated
Hours Hourly Rate Costs
8 $ 50.00 $ 400
7 52.18 365
20 50.00 1,000
34 35.84 1,219
6 25.99 156
7 22.05 154
| 82 Total Direct Labor $ 3,294
Indirect Costs @ 1.7 5,600
Subtotal $ 8,894
Fixed Fee $ 889
Subtotal $ 9,783
Direct Costs $ 205
CLD Total Estimated Cost: “$ 9,988
Haley & Aldrich, Inc. $ 1,500
TOTAL ESTIMATED COST: 11,488
-l- 6/2018