Documents. Shop Drawings, Product Data, Samples and similar submittals are
not Contract Documents.
12.The Contractor shall confine operations at the site to areas permitted by law,
ordinances, permits, the Contract Documents and the Owner.
13.The Contractor shall be responsible for cutting, fitting or patching required to
complete the Work or to make its parts fit together properly.
14.The Contractor shall keep the premises and surrounding area free from
accumulation of debris and trash related to the Work.
15.Contractor warrants and guarantees to Owner, for one year, upon completion of
work, that all Work will be in accordance with the Contract Documents and will
not be defective. Contractors warranty and guarantee hereunder excludes
defects or damage caused by:
A. Abuse, modification, or improper maintenance or operation by persons other
than Contractor, Subcontractors, Suppliers, or any other individual or entity
for whom Contractor is responsible; or
B. Normal wear and tear under normal usage.
ARTICLE 8 - CHANGES IN THE WORK
1.
After execution of the Contract, changes in the Work may be accomplished by
Change Order or by order for a minor change in the Work. The Owner, without
invalidating the Contract, may order changes in the Work within the general
scope of the Contract consisting of additions, deletions or other revisions, the
Contract Sum and Contract Time being adjusted accordingly.
A Change Order shall be a written order to the Contractor signed by the Owner to
change the Work, Contract Sum or Contract Time.
Change Order requests must include material and equipment cost plus labor with
a profit margin of no more than 10%. Change Orders may require approval by
the Community Development Division Director and the City of Nashua Finance
Committee vote prior to proceeding.
The Owner will have authority to order minor changes in the Work not involving
changes in the Contract Sum or the Contract Time and not inconsistent with the
intent of the Contract Documents. Such changes shall be written orders and
shall be binding on the Owner and Contractor. The Contractor shall carry out
such written orders promptly.
. If concealed or unknown physical conditions are encountered at the site that
differ materially from those indicated in the Contract Documents or from those
conditions ordinarily found to exist, the Contract Sum and Contract Time shall be
subject to equitable adjustment following authorization of the Owner to the
charges.